Nvidia Sells GPUs, Then Buys Customers' Cloud Services: $36 Billion in Commitments Stirs Debate
Deals that bundle GPU sales with cloud usage commitments are drawing scrutiny. Nvidia says it is helping AI companies secure computing capacity, while The Wall Street Journal reports that executives worried about the size of the guarantees.

Nvidia is facing questions over financing arrangements designed to help AI companies secure data center capacity. On November 13, The Wall Street Journal reported, citing unnamed sources, that Nvidia executives were concerned about the scale of the guarantees and profitability. TechPowerUp picked up the report and raised the possibility that Nvidia’s investments had artificially inflated an existing shortage of GPUs and memory.
Selling GPUs and buying customers’ cloud services: how the structure works
The arrangements Nvidia has disclosed tie product sales and cloud service usage together. When certain AI cloud companies buy Nvidia’s data center products, Nvidia commits to using those companies’ cloud services. The company selling the hardware also becomes a customer of the company buying it.
The cloud providers can also sell that capacity to other customers on better terms. As of July 26, 2026, Nvidia’s disclosed cloud usage commitments totaled $36 billion. The contracts typically run six years.
In its August earnings announcement, Nvidia said its investments and credit support were meant to help AI companies secure computing infrastructure. The company also acknowledged that some observers view these deals as “circular financing.” The flow of money sits at the center of the debate: the company selling the equipment supports the buyer, which then turns around and buys that same equipment.
What exactly is the $105 billion guarantee?
Separate from the service usage commitments, there are also data center guarantees. In the same disclosure, Nvidia’s guarantee cap for certain AI cloud companies’ data center lease obligations is $3.5 billion. The guarantee cap for an OpenAI-related data center project in Ohio is $105 billion.
The Ohio guarantee comes with conditions. It takes effect only as facilities are completed in phases and leases begin, and it applies only to specified rent and a portion of power costs. Nvidia disclosed that customer funding shortfalls or delays in data center construction could slow product deployments and affect its financial results. The Wall Street Journal reported that executives were concerned not only about the guarantees and profitability but also about the volume of chip supply the company has already committed to securing.
In 2025, Nvidia announced a letter of intent with OpenAI to build at least 10 gigawatts of Nvidia systems. The investment plan outlined at the time was for up to $100 billion, to be deployed in tranches as the facilities progress.
What to watch next
At its core, this debate is about how the equipment and data centers underpinning AI services get financed. Two things are worth watching: how much of the commitments and guarantees actually translate into built facilities, and how much customer funding conditions or construction delays slow equipment deployment. Those are precisely the risks Nvidia flagged in its own disclosures.